Protected Distribution System Extension – Bldg. 12010 | Fort Hood, TX
August 15, 2017

Performance Oriented Contract Award (POCA) for Renovations and New Construction | Tinker AFB, OK

Project Description:

GD will remove, replace and/or install a new parking lot, sidewalks and provide drainage improvements at various locations on Tinker AFB for USACE. GD will also furnish all design/engineering services, plant, labor, equipment, instruments, materials, transportation, and incidentals required to repair sidewalks, footpads, pavement, and drainage at B412 and B1022.


Services Provided:

Design-Build

Date of Construction Start:

April 27, 2017

Date of Construction Finish:

June 5, 2017

Construction Contract Value: (GD)

$207,330.46